City of McAllen Highlights $610k Major Drainage Improvements in Balboa Acres

Translate text to Spanish or other 102 languages!

- Advertisement -
City of McAllen leaders celebrated the completion of critical drainage upgrades in the Balboa Acres area, reinforcing the community’s flood resilience and safety. Courtesy image
- Advertisement -

McALLEN, Texas – City of McAllen leaders celebrated the completion of critical drainage upgrades in the Balboa Acres area, reinforcing the community’s flood resilience and safety. The project included replacing five outdated, manually operated sluice gates with advanced automatic check valves designed to prevent backflow during heavy rain events. Additional improvements featured new headwalls, spillways, and erosion-control measures, ensuring long-term protection for residents and infrastructure.

Officials celebrate the day with an official Ribbon cutting for the Balboa Acres Drainage project. Courtesy image
Project Cost: $610, 752.76
Participating Agencies: City of McAllen
Fund: Drainage Fee Fund
Contractor: Diverse Construction
Engineer: Perez Consulting Engineers
Complete Construction Timeline: February 2025 through September 2025
Part of the Balboa Project. Courtesy image

Information source: The City of McAllen