Construction on New Hidalgo County Courthouse, set for completion November 10, 2021. Image courtesy of Jacobs.

Texas Border Business

Jacob’s Project Mgr. Oscar Garcia

Progress on the courthouse construction is on track, said Courthouse Project Manager Oscar Garcia, with Jacobs.

At Tuesday’s meeting, Garcia reported that structural construction on the courthouse building is complete, which includes interior framing, installation of drywall, and site utilities. Crews continue to work on sanitary sewer connections and staircases.  

“We continue to have good progress,” said Garcia. “The first four levels of the New Hidalgo County Courthouse will be completed by July 13, 2021, and the remainder will be completed by November 10, 2021. We are on track.”

For new courthouse construction updates, please click here.